Design Schedule for New Construction and Renovation projects
New Construction:
Bainbridge Branch
Thompson Branch
Renovations:
Middlefield Branch
Geauga West Branch
Chardon Branch
Arch. Project No. 11989.00
Selection:
Date Issuance
04/30/2018: Site Tours
05/01/2018: Steering Committee Meetings
05/02/2018: Steering Committee Meetings.
05/08/2018: Construction Budgets Draft Hard Vs. Soft Cost
05/11/2018: CMR Proposal Meeting
05/14/2018: Release Survey and Boring Activity for New Construction Sites
05/15/2018: Announcement Public Marketing
05/18/2018: CMR Proposal
05/29/2018: 50% Program Complete
05/31/2018: Soil and Survey Report
06/04/2018: Review CMR Proposal
06/12/2018: CM Interview – Public Meeting 1 Bainbridge Branch
6/13/2018 Public Meeting 1 Thompson Branch – Steering Committee Meetings
06/20/2018 100% Program and Schedule Deliverable
07/17/2018 Public Meeting 2 Thompson Branch
07/18/2018 Public Meeting 2 Bainbridge Branch – Steering Committee Meetings
Design:
Date Issuance
08/01/2018 50% Schematic Design Complete
08/21/2018 Geauga Board Meeting
08/31/2018 95% Schematic Design Complete – Issue to CM for Pricing
09/21/2018 100% Schematic Design Complete Issuance – CMR Estimate
09/25/2018 Library Board Meeting to Review/Approve SD – Design Team Meeting
09/28/2018 Chardon Decision – 1M Reno or 4.6M Addition
10/02/2018 Schematic Design Approval (New Construction and Renovation)
10/03/2018 Start of Design Development (New Construction and Renovation)
10/16/2018 Public Meeting 3 (Showing Concepts) – Steering Committee Meetings
10/17/2018 Public Meeting 3 (Showing Concepts)
11/20/2018 Steering Committee Meetings
11/30/2018 95% Design Development Complete (New Builds) – Issue for Pricing to CMR
12/05/2018 95% Design Development Complete (Renovations) – Issue for Pricing to CMR
12/12/2018 100% Design Development (New Construction) – CMR Estimate
12/21/2018 100% Design Development (Renovations) – CMR Estimate
01/08/2019 Design Development Approval (New Construction and Renovation)
01/09/2019 Start Construction Documents (New Construction and Renovation)
02/19/2019 Steering Committee Meetings
02/20/2019 90% Construction Documents (Renovations) – Issue for to CMR for GMP
03/13/2019 GMP for Renovations Due to Library
03/19/2019 Library Board Meeting (approve GMP of Renovations)
03/27/2019 100% Construction Documents Complete (Renovations) – Issue for Construction/Permit
04/05/2019 90% Construction Documents (New Construction) – Issue for to CMR for GMP
04/24/2019 Renovation Permits Available
04/26/2019 GMP for New Builds Due to Library
Construction:
Date Issuance
04/29/2019 Renovation Construction Start
04/30/2019 Board Approval of New Build GMP
05/10/2019 100% Construction Documents Complete (New Construction) – Issue for Construction/Permit
06/07/2019 New Build Permits Available
06/10/2019 New Build Construction Start
10/2019 Geauga West Branch Completion
10/2019 Middlefield Branch Completion
05/2020 Thompson Branch Completion
09/2020 Bainbridge Branch Completion